April 2014

  • Column casting at fourth floor in progress and brick work at first floor in progress View: Block M 01
    Progress: Column casting at fourth floor in progress and brick work at first floor in progress
  • Fourth floor roof slab completed & brick work at first Floor in progress View: Block M 02
    Progress: Fourth floor roof slab completed & brick work at first Floor in progress
  • Lift machine room slab reinforcement work in progress and brickwork at second floor work in progress View: Block M 03
    Progress: Lift machine room slab reinforcement work in progress and brickwork at second floor work in progress
  • Lift machine room columns comleted and brickwork at second floor in progress View: Block M 04
    Progress: Lift machine room columns comleted and brickwork at second floor in progress
  • Lift machine room slab completed & columns reinforcement of overhead water tank work in progress View: M 05
    Progress: Lift machine room slab completed & columns reinforcement of overhead water tank work in progress
  • Balcony brickwork in progress, internal plaster work in progress View: M 06
    Progress: Lift machine room & overhead water tank base slab completed, balcony brickwork in progress, internal plaster work in progress
  • Ground floor columns and slab/beam shuttering work in progress View: M 07
    Progress: Ground floor columns and slab/beam shuttering work in progress
  • Reinforcement and shuttering of columns at first floor in progress View: M 08
    Progress: Reinforcement and shuttering of columns at first floor in progress
  • Fourth floor roof slab completed and brickwork at second floor in progress View: M 09
    Progress: Fourth floor roof slab completed and brickwork at second floor in progress
  • Fourth floor roof slab completed and brickwork at first floor in progress View: M 10
    Progress: Fourth floor roof slab completed and brickwork at first floor in progress
  • Backfilling work in progress View: M 11
    Progress: Backfilling work in progress
  • 25% Plinth beam completed and remaining work in progress View: M 12
    Progress: 25% Plinth beam completed and remaining work in progress
  • Column reinforcement work in progress at first floor slab; brickwork at ground flor in progress View: M 14
    Progress: Column reinforcement work in progress at first floor slab; brickwork at ground flor in progress
  • Second floor roof slab/beam shuttering in progress; brickwork at ground floor in progress View: M 15
    Progress: Second floor roof slab/beam shuttering in progress; brickwork at ground floor in progress
  • Columns reinforcement at first floor in progress View: M 16
    Progress: Columns reinforcement at first floor in progress
  • Ground floor columns reinforcement and columns casting work in progress View: M 17
    Progress: Ground floor columns reinforcement and columns casting work in progress
  • Footings completed and pedastl work in progress View: M 18 & 19
    Progress: Footings completed and pedastl work in progress
  • Columns at first floor completed View: M 20
    Progress: Columns at first floor completed
  • Columns reinforcement work at first floor in pro View: M 21
    Progress: Columns reinforcement work at first floor in progress
  • 50% Ground floor slab completed and remaing part reinforcement of slab/beam in progress View: M 22
    Progress: 50% Ground floor slab completed and remaing part reinforcement of slab/beam in progress
  • 60% Plinth beam completed and remining work in progress View: M 23
    Progress: 60% Plinth beam completed and remining work in progress
  • Pedestels work in progress View: M 24 & 25
    Progress: Pedestels work in progress
  • Pedestels work in progress View: M 26 & 27
    Progress: Pedestels work in progress
  • Brickwork at second floor in progress View: M 28
    Progress: Brickwork at second floor in progress
  • Fourth floor roof slab completed and brickwork at first floor in progress View: M 29
    Progress: Fourth floor roof slab completed and brickwork at first floor in progress
  • First floor roof slab work in progress View: M 30
    Progress: First floor roof slab work in progress
  • 50% Third floor roof slab completed and in remaining part shuttering of slab/bam work and columns casting work in progress View: M 31
    Progress: 50% Third floor roof slab completed and in remaining part shuttering of slab/bam work and columns casting work in progress
  •  
  •  