August 2013

  • Plinth Beam In Progress (Block M-5)
  • Ground Floor Slab Shuttering (Block M-6)
  • Column Upto Plinth Beam In Progress (Block M-4)
  • View: Block M 01 & M 02
    Progress: Column upto plinth beam in progress
  • Pedestal Work In Progress (Block M-1 & M-2)
  • Footing & Pedestal Work In Progress (Block M-9 & M-10)
  • Excavation Work Completed (Block M-11 & M-12)
  • Excavation Work In Progress (Block M-14 & M-15)