December 2014

  • EXTERNAL & INTERNAL PLASTER WORK IN PROGRESS View: Block M 01
    Progress: External & Internal Plaster Work In Progress
  • EXTERNAL PLASTER WORK IN PROGRESS View: Block M 02
    Progress: Plumbing, Internal & External Plaster Work In Progress
  • PLUMBING WORK IN PROGRESS View: Block M 03
    Progress: Internal, External Plaster & Plumbing Work In Progress
  • INTERNAL PLASTER & PLUMBING WORK IN PROGRESS View: M 04
    Progress: Internal Plaster & Plumbing Work In Progress
  • INTERNAL PLUMBING WORK IN PROGRESS View: M 05
    Progress: Internal Plumbing Work In Progress
  • TILING WORK IN PROGRESS View: M 06
    Progress: Tiling Work In Progress
  • BRICK WORK COMPLETED UP TO 4TH FLOOR View: M 07
    Progress: Brick Work Completed Up To 4th Floor
  • BRICK WORK COMPLETED UP TO 4TH FLOOR View: M 08
    Progress: Brick Work Completed Up To 4th Floor
  • BRICK WORK UP TO 4TH FLOOR COMPLETED View: Block M 09
    Progress: Brick Work Up To 4th Floor Completed
  • BRICK WORK UP TO 4TH FLOOR COMPLETED View: M 10
    Progress: Brick Work Up To 4th Floor Completed
  • 3RD FLOOR ROOF SLAB IN PROGRESS View: M 11
    Progress: 3rd Floor Roof Slab In Progress
  • COLUMNS FOR TERRACE FLOOR IN PROGRESS View: Block M 12
    Progress: Columns For Terrace Floor In Progress
  • BRICK WORK AT TERRACE IN PROGRESS View: Block M 14
    Progress: Brick Work At Terrace In Progress
  • COLUMNS FOR TERRACE IN PROGRESS View: Block M15
    Progress: Brick Work Of Parapet Wall In Progress
  • BRICK WORK OF PARAPET WALL IN PROGRESS View: M 16
    Progress: Columns For Terrace In Progress
  • 3RD FLOOR ROOF IN PROGRESS View: M 17
    Progress: 3rd Floor Roof In Progress
  • 3RD FLOOR ROOF IN PROGRESS View: M 18
    Progress: 3rd Floor Roof In Progress
  • TERRACE SLAB IN PROGRESS View: M 19
    Progress: Terrace Slab In Progress
  • TERRACE SLAB CASTED View: M 20
    Progress: Terrace Slab Casted
  • 2ND FLOOR ROOF CASTED View: M 21
    Progress: 2nd floor roof casted
  • 3RD FLOOR ROOF IN PROGRESS View: Block M 22
    Progress: 3rd floor roof in progress
  • 3RD FLOOR ROOF CASTED View: M 23
    Progress: 3rd floor roof casted
  • 2ND FLOOR ROOF 50% CASTED View: M 24
    Progress: 2nd floor roof 50% casted
  • 2ND FLOOR ROOF 50% CASTED View: M 25
    Progress: 2nd floor roof 50% casted
  • 1ST FLOOR ROOF IN PROGRESS View: M 26
    Progress: 1st floor roof in progress
  • 1ST FLOOR ROOF IN PROGRESS View: M 27
    Progress: 1st floor roof in progress
  • TERRACE PARAPET COMPLETED View: M 28
    Progress: Terrace parapet completed
  • TERRACE PARAPET COMPLETED View: M 29
    Progress: Terrace parapet completed
  • BRICK WORK AT 4TH FLOOR COMPLETED View: Block M 30
    Progress: Brick work at 4th floor completed
  • FOURTH FLOOR ROOF SLAB CASTED AND BRICK WORK UP TO 4TH FLOOR COMPLETED View: M 31
    Progress: Fourth floor roof slab casted and brick work up to 4th floor completed