January 2014

  • Upcoming Residential Project in Meerut View: Site cum society office
    Progress: Work completed
  • New Projects in Meerut - VIEW: BLOCK M 01 View: M 01
    Progress: First floor roof slab completed and second floor column reinforcement work in progress
  • Upcoming Project in Meerut : VIEW: M 02 View: M 02
    Progress: Second floor slab reinforcement work in progress and brick- work at first floor in progress
  • Residential Construction Projects : VIEW: M 03 View: M 03
    Progress: Fourth floor columns reinforcement work in progress

  • Real Estate Projects in Meerut : VIEW: M 04 View: M 04
    Progress: Third floor columns casting in progress
  • Residential Property in Meerut : VIEW: BLOCK M 05 View: M 05
    Progress: Lift machine room & over head tank work in progress and brickwork at 4th floor in progress
  • Residential Projects in Meerut : VIEW: BLOCK M 06 View: M 06
    Progress: Lift machine room & over head tank in progress and internal plaster in progress
  • Meerut Properties : VIEW: M 7 View: M 07
    Progress: Backfilling work in progress
  • Meerut Residential Properties : VIEW: M 8 View: M 08
    Progress: Plinth beam reinforcement work in progress
  • Meerut Upcoming Projects : VIEW: M 9 View: M 09
    Progress: Third floor slab casting work in progress
  • Meerut Residential Projects : VIEW: M 10 View: M 10
    Progress: First floor slab reinforcement work in progress
  • Meerut New Projects : VIEW: M 11 & 12 View: M 11 & 12
    Progress: Backfilling work in progress
  • VIEW: M 14 : PLINTH BEAM WORK IN PROGRESS View: M 14
    Progress: Plinth beam work in progress
  • VIEW: M 15 : GROUND FLOOR COLUMNS CASTING WORK IN PROGRESS View: M 15
    Progress: Ground floor columns casting work in progress
  • VIEW: M 16 : PLINTH BEAM CASTING IN PROGRESS View: M 16
    Progress: Ground floor columns castings and plinth beam casting in progress
  • VIEW: M 17 & 18 : PLINTH BEAM SHUTTERING, PEDESTALS WORK IN PROGRESS View: M 17 & 18
    Progress: Plinth beam shuttering work in progress in m 17 & pedestals work in progress in m18
  • VIEW: M 20 : GROUND FLOOR SLAB SHUTTERING WORK IN PROGRESS View: M 20
    Progress: Ground floor slab shuttering work in progress
  • VIEW: M 21 : PLINTH BEAM COMPLETED View: M 21
    Progress: Plinth beam completed
  • VIEW: M 22 : PLINTH BEAM WORK IN PROGRESS View: M 22
    Progress: Plinth beam work in progress
  • VIEW: M 23 : PEDESTALS CASTING WORK IN PROGRESS View: M 23
    Progress: Pedestals casting work in progress
  • VIEW: M 24 & 25 : PEDESTALS CASTING WORK IN PROGRESS View: M 24 & 25
    Progress: Pedestals casting work in progress
  • VIEW: M 26 & 27 : PEDESTALS CASTING WORK IN PROGRESS View: M 26 & 27
    Progress: Pedestals casting work in progress
  • VIEW: M 28 : THIRD FLOOR COLUMNS CASTING WORK IN PROGRESS View: M 28
    Progress: Third floor columns casting work in progress
  • VIEW: M 29 : REINFORCEMENT WORK IN PROGRESS View: M 29
    Progress: 50% second floor salb completed and in remaining part reinforcement work in progress
  • VIEW: M 30 : GROUND FLOOR COLUMNS CASTING WORK IN PROGRESS View: M 30
    Progress: Ground floor columns casting work in progress
  • VIEW: M 31 : GROUND FLOOR SLAB RENFORCEMENT WORK IN PROGRESS View: M 31
    Progress: Ground floor slab renforcement work in progress
  •  
  •  
  •  
  •  
  •  
  •  