  • External & Internal Plumbing In Progress View: Block M 01
    Progress: External & Internal Plumbing In Progress
  • Plumbing, External & Internal Plaster In Progress View: Block M 02
    Progress: Plumbing, External & Internal Plaster In Progress
  • Internal & External Plaster & Plumbing Work In Progress View: Block M 03
    Progress: Internal & External Plaster & Plumbing Work In Progress
  • Internal Plaster & Plumbing Work In Progress View: Block M 04
    Progress: Internal Plaster & Plumbing Work In Progress
  • Tiling Work In Progress View: Block M 05
    Progress: Tiling Work In Progress
  • Tiling Work In Progress View: Block M 06
    Progress: Tiling Work In Progress
  • Internal Plaster & Plumbing Work In Progress View: Block M 07
    Progress: Internal Plaster & Plumbing Work In Progress
  • Internal Plaster & Plumbing Work In Progress View: Block M 08
    Progress: Internal Plaster & Plumbing Work In Progress
  • Internal Plaster & Plumbing Work In Progress View: Block M 09
    Progress: Internal Plaster & Plumbing Work In Progress
  • Internal Plaster & Plumbing Work In Progress View: Block M 10
    Progress: Internal Plaster & Plumbing Work In Progress
  • Third Floor Roof Slab Completed View: Block M 11
    Progress: Third Floor Roof Slab Completed
  • Columns For Terrace Floor In Progress View: Block M 12
    Progress: Columns For Terrace Floor In Progress
  • Over Terrace Activities In Progress View: Block M 14
    Progress: Over Terrace Activities In Progress
  • Over Terrace Activities In Progress View: Block M15
    Progress: Over Terrace Activities In Progress
  • Structure Upto Terrace Completed View: Block M 16
    Progress: Structure Upto Terrace Completed
  • 4th To Terrace Floor Columns In Progress View: Block M 17
    Progress: 4th To Terrace Floor Columns In Progress
  • 4th To Terrace Floor Columns In Progress View: Block M 18
    Progress: 4th To Terrace Floor Columns In Progress
  • Terrace Slab Completed View: Block M 19
    Progress: Terrace Slab Completed
  • Terrace Slab Casted View: Block M 20
    Progress: Terrace Slab Casted
  • 3rd Floor Roof In Progress View: Block M 21
    Progress: 3rd Floor Roof In Progress
  • 4th To Terrace Columns In Progress View: Block M 22
    Progress: 4th To Terrace Columns In Progress
  • Terrace Slab In Progress View: Block M 23
    Progress: Terrace Slab In Progress
  • 2nd Floor Roof 50% Casted View: Block M 24
    Progress: 2nd Floor Roof 50% Casted
  • 2nd Floor Roof 50% Casted View: Block M 25
    Progress: 2nd Floor Roof 50% Casted
  • Second Floor Roof In Progress View: Block M 26
    Progress: Second Floor Roof In Progress
  • Second Floor Roof In Progress View: Block M 27
    Progress: Second Floor Roof In Progress
  • Terrace Parapet Completed View: Block M 28
    Progress: Terrace Parapet Completed
  • Terrace Parapet Completed View: Block M 29
    Progress: Terrace Parapet Completed
  • Brickwork At Fourth Floor Completed View: Block M 30
    Progress: Brickwork At Fourth Floor Completed
  • Fourth Floor Roof Slab Casted View: Block M 31
    Progress: Fourth Floor Roof Slab Casted And Brickwork Upto Fourth Floor Completed