June 2014

  • FOURTH FLOOR ROOF SLAB & BRICK WORK AT FIRST FLOOR COMPLETED View: Block M 01
    Progress: Fourth floor roof slab & brick work at first floor completed
  • FOURTH FLOOR ROOF SLAB COMPLETED & BRICK WORK AT FIRST FLOOR COMPLETED View: Block M 02
    Progress: Fourth floor roof slab completed & brick work at first floor completed
  • LIFT MACHINE ROOM SLAB REINFORCEMENT WORK IN PROGRESS View: Block M 03
    Progress: Lift machine room slab reinforcement work in progress and brickwork at second and fourth floor completed
  • LIFT MACHINE ROOM SLAB REINFORCEMENT WORK IN PROGRESS View: Block M 04
    Progress: Lift machine room slab reinforcement work in progress and brickwork at second and fourth floor completed
  • LIFT MACHINE ROOM SLAB COMPLETED View: M 05
    Progress: Lift machine room slab completed& columns reinforcement of overhead water tank in progress
  • LIFT MACHINE ROOM SLAB COMPLETED View: M 06
    Progress: Lift machine room slab completed, balcony railing in progress, internal plaster at third floor completed. External plaster in progress
  • SECOND FLOOR CASTED View: M 07
    Progress: Second floor casted
  • SECOND FLOOR CASTED View: M 08
    Progress: Second floor casted and reinforcement and shuttering of columns at third floor in progress.
  • FOURTH FLOOR ROOF SLAB COMPLETED View: M 09
    Progress: Fourth floor roof slab completed & Brickwork at second floor in progress
  • SLAB FOURTH FLOOR ROOF COMPLETED AND FIRST & SECOND FLOOR BRICKWORK IN PROGRESS View: M 10
    Progress: Fourth floor roof slab completed and first & second floor brickwork in progress
  • PLINTH BEAM WORK IN PROGRESS View: M 11
    Progress: Plinth beam work in progress
  • GROUND FLOOR ROOF SLAB R/F WORK IN PROGRESS WORK IN PROGRESS View: M 12
    Progress: Ground floor roof slab r/f work in progress work in progress
  • SECOND FLOOR ROOF SLAB COMPLETED View: M 14
    Progress: Second floor roof slab completed and slab shuttering work in progress at third floor
  • SECOND FLOOR ROOF SLAB COMPLETED AND SLAB SHUTTERING WORK IN PROGRESS AT THIRD FLOOR View: M 15
    Progress: Second floor roof slab completed and slab shuttering work in progress at third floor. brick work in progress at first floor
  • FIRST FLOOR SLAB COMPLETED View: M 16
    Progress: First floor slab completed
  • GROUND FLOOR SLAB CASTED.SLAB SHUTTERING FOR FIRST FLOOR IN PROGRESS View: M 17
    Progress: Ground floor slab casted.slab shuttering for first floor in progress
  • GROUND FLOOR SLAB SHUTTERING IN PROGRESS View: M 18
    Progress: Ground floor slab shuttering in progress
  • PLINTH BEAM WORK IN PROGRESS View: M 19
    Progress: Plinth beam work in progress
  • SLAB REINFORCEMENT AT FIRST FLOOR ROOF IN PROGRESS View: M 20
    Progress: Slab reinforcement at first floor roof in progress
  • GROUND FLOOR ROOF SLAB COMPLETED View: M 21
    Progress: Ground floor roof slab completed and slab shuttering work in progress at first floor
  • GROUND FLOOR ROOF SLAB COMPLETED View: M 22
    Progress: Ground floor roof slab completed. columns for first floor in progress
  • GROUND FLOOR SLAB COMPLETED View: M 23
    Progress: Ground floor slab completed
  • COLUMNS FOR GROUND FLOOR ROOF SLAB IN PROGRESS View: M 24
    Progress: Columns for ground floor roof slab in progress
  • PLINTH BEAM WORK IN PROGRESS View: M 25
    Progress: Plinth beam work in progress
  • PLINTH BEAM AND FILLING WORK IN PROGRESS View: M 26 & 27
    Progress: Plinth beam and filling work in progress
  • FOURTH FLOOR ROOF SLAB WORK COMPLETED View: M 28
    Progress: Fourth floor roof slab work completed and brickwork at fourth floor in progress
  • FOURTH FLOOR ROOF SLAB WORK COMPLETED View: M 29
    Progress: Fourth floor roof slab work completed and brickwork at fourth floor in progress
  • FOURTH FLOOR ROOF SLAB CASTED AND BRICK WORK AT GROUND FLOOR COMPLETED View: M 30
    Progress: Fourth floor roof slab casted and brick work at ground floor completed
  • FOURTH FLOOR ROOF SLAB CASTED AND BRICKWORK IN PROGRESS AT FIRST FLOOR View: M 31
    Progress: Fourth floor roof slab casted and brickwork in progress at first floor
  •  
  •  