  • THIRD FLOOR ROOF SLAB COLUMN CASTING WORK IN PROGRESS View: Block M 01
    Progress: Third floor roof slab column casting work in progress and brick work at first floor in progress
  • FOURTH FLOOR ROOF SLAB COLUMN REINFORCEMENT WORK IN PROGRESS View: Block M 02
    Progress: Fourth floor roof slab column reinforcement work in progress & brick work at first floor in progress
  • BRICKWORK AT SECOND FLOOR WORK IN PROGRESS View: Block M 03
    Progress: Fourth floor roof slab completed and brickwork at Second floor work in progress
  • BRICKWORK AT FIRST FLOOR IN PROGRESS View: Block M 04
    Progress: Fourth floor roof slab completed and brickwork at First floor in progress
  • LIFT MACHINE ROOM & OVERHEAD WATER TANK WORK IN PROGRESS View: M 05
    Progress: Lift machine room & overhead water tank work in progress
  • BALCONY BRICKWORK IN PROGRESS, INTERNAL PLASTER WORK IN PROGRESS View: M 06
    Progress: Lift machine room & overhead water tank base slab completed, balcony brickwork in progress, internal plaster work in progress
  • 50 % PLINTH BEAM WORK COMPLETED & WORK IN PROGRESS View: M 07
    Progress: 50 % plinth beam work completed & work in progress
  • CASTING OF COLUMNS AT GROUND FLOOR IN PROGRESS View: M 08
    Progress: Plinth beam work completed and casting of columns at Ground floor in progress
  • FOURTH FLOOR ROOF SLAB WORK IN PROGRESS View: M 09
    Progress: Fourth floor roof slab work in progress and Brickwork at second floor in progress
  • GROUND FLOOR BRICKWORK IN PROGRESS View: M 10
    Progress: Third floor roof slab completed and ground floor Brickwork in progress
  • BACKFILLING WORK IN PROGRESS View: M 11 & 12
    Progress: Backfilling work in progress
  • 50 % GROUND FLOOR ROOF SLAB COMPLETED AND WORK IN PROGRESS View: M 14
    Progress: 50 % Ground floor roof slab completed and Work in progress
  • COLUMN REINFORCEMENT WORK IN PROGRESS AT FIRST FLOOR SLAB View: M 15
    Progress: Ground floor roof slab completed and column reinforcement work in progress at first floor slab
  • COLUMNS CASTING AT GROUND FLOOR COMPLETED View: M 16
    Progress: Columns casting at ground floor completed
  • PLINTH BEAM COMPLETED View: M 17
    Progress: Plinth beam completed
  • PEDESTELS WORK IN PROGRESS View: M 18
    Progress: Pedestels work in progress
  • FOOTING WORK IN PROGRESS View: M 19
    Progress: Footing work in progress
  • COLUMNS CASTING AT FIRST FLOOR IN PROGRESS View: M 20
    Progress: Ground floor roof slab completed and columns casting at first floor in progress
  • GROUND FLOOR ROOF SLAB REINFORCEMENT AND SHUTTERING WORK IN PROGRESS View: M 21
    Progress: Ground floor roof slab reinforcement and shuttering work in progress
  • PLINTH BEAM COMPLETED AND BACKFILLING WORK IN PROGRESS View: M 22
    Progress: Plinth beam completed and backfilling work in progress
  • PLINTH BEAM SHUTTERING WORK IN PROGRESS View: M 23
    Progress: Plinth beam shuttering work in progress
  • VIEW: M 24 & 25 : PEDESTELS WORK IN PROGRESS View: M 24 & 25
    Progress: Pedestels work in progress
  • VIEW: M 26 & 27 : PEDESTELS WORK IN PROGRESS View: M 26 & 27
    Progress: Pedestels work in progress
  • FOURTH FLOOR ROOF SLAB COMPLETED AND BRICKWORK AT FIRST FLOOR IN PROGRESS View: M 28
    Progress: Fourth floor roof slab completed and brickwork at first floor in progress
  • FOURTH FLOOR ROOF SLAB WORK IN PROGRESS AND BRICKWORK AT FIRST FLOOR IN PROGRESS View: M 29
    Progress: Fourth floor roof slab work in progress and brickwork at first floor in progress
  • FIRST FLOOR ROOF SLAB WORK IN PROGRESS View: M 30
    Progress: First floor roof slab work in progress
  • SECOND FLOOR ROOF SLAB SHUTTERING WORK AND COLUMNS CASTING WORK IN PROGRESS View: M 31
    Progress: Second floor roof slab shuttering work and columns casting work in progress
  •  
  •  
  •  
  •  
  •  