September 2013

  • View: Block M 06
    Progress: Column of 2nd floor slab in progress
  • View: Block M 05
    Progress: Reinforcement laying of ground floor roof slab in progress
  • View: Block M 03 & M 04
    Progress: Shuttering of plinth beam in progress
  • View: Block M 01 & M 02
    Progress: Column upto plinth beam in progress
  • View: Site cum society office
    Progress: Plaster work in progress
  • View: M 09 & M 10
    Progress: Shuttering & reinforcement of plinth beam in progress
  • View: M 11 & M 12
    Progress: Footing of rcc work in progress
  • View: M 14 & M 15
    Progress: Footing of rcc work in progress
  • View: M 24 & M 27 Progress: PCC work completed
  • View: M 16 & M 19
    Progress: PCC work in progress
  • View: M 28 & M 29
    Progress: PCC work completed
  • View: M 30 & M 31
    Progress: PCC work completed
  •  
  •  
  •  
  •  